APC 3 Phase UPS; Installation of dual mains or two sources input to UPS; where does the neutral conductor get terminated?

Product line:
APC 3 Phase UPS

Environment:
All models, all serial numbers

Cause:
Installation of dual mains or two sources input to UPS; where does the neutral conductor get terminated?

Resolution:
In the USA when we have two sources we feed the rectifier input (mains1) as 3-phase +PE and the bypass (mains2) as 3-phase +N+PE. We do this because the neutral bus in the UPS is common to both inputs and output and the battery system mid-point.

Our National Electrical Code forbids connecting the two source neutrals together. Also with the common neutral bus in the UPS you can get circulating currents flowing between the two transformers and also ground fault current from upstream system loads flowing in the UPS neutral bus. Therefore it is not recommend having input neutral on the rectifier feeder (mains1) for dual feed systems.”

3 phase wiring diagram

Schneider Electric Česká republika

APC 3 Phase UPS; dual feed UPS systems, where does the neutral conductor get terminated?

Article available in these languages: Španělština

Issue:
APC 3 Phase UPS; Installation of dual mains or two sources input to UPS; where does the neutral conductor get terminated?

Product line:
APC 3 Phase UPS

Environment:
All models, all serial numbers

Cause:
Installation of dual mains or two sources input to UPS; where does the neutral conductor get terminated?

Resolution:
In the USA when we have two sources we feed the rectifier input (mains1) as 3-phase +PE and the bypass (mains2) as 3-phase +N+PE. We do this because the neutral bus in the UPS is common to both inputs and output and the battery system mid-point.

Our National Electrical Code forbids connecting the two source neutrals together. Also with the common neutral bus in the UPS you can get circulating currents flowing between the two transformers and also ground fault current from upstream system loads flowing in the UPS neutral bus. Therefore it is not recommend having input neutral on the rectifier feeder (mains1) for dual feed systems.”

  3 phase wiring diagram

Schneider Electric Česká republika

Zjistěte více
Řada:
Zjistěte více
Řada:
Zjistěte více
Řada:
Zjistěte více
Řada:
move-arrow-top
Your browser is out of date and has known security issues.

It also may not display all features of this website or other websites.

Please upgrade your browser to access all of the features of this website.

Latest version for Google Chrome, Mozilla Firefox or Microsoft Edgeis recommended for optimal functionality.
Your browser is out of date and has known security issues.

It also may not display all features of this website or other websites.

Please upgrade your browser to access all of the features of this website.

Latest version for Google Chrome, Mozilla Firefox or Microsoft Edgeis recommended for optimal functionality.